Cumberland County Road Project Updates Now on Web
The public can now follow the progress of a long list of road improvement projects underway across Cumberland County, right on their computers.
The Department of Public Works in collaboration with the county IT department have added a link on upper right corner of the county’s website (cumberlandcountynj.gov).
The list includes federally and state-funded road improvement projects.
Among the larger projects nearing completion this week, Brewster Road in Vineland.
As crews wrap up work on summer projects, a number of others will be starting in coming weeks.
2013 Public Works Project Update
2012 Federal Highway Administration Funded Road Program – 2.1 million
- Brewster Rd – Completed except for punch list items.
- Lincoln Ave – Drainage complete, installing electrical for traffic signal replacement, mill and overlay to follow
- Union Rd. – Completed except for punch list items
2013 NJDOT Funded Road Program 5.79 million
- Glade Rd – Drainage complete, mill and overlay to follow
- Polk Lane – Drainage complete, mill and overlay to follow
- Burlington Rd – Drainage in process
- Wheaton Island – Drainage complete, mill and overlay to follow
- Newport Neck Rd – Drainage complete, mill and overlay to follow
- Vineland Ave – Drainage to begin week of Sept. 2nd
- Fairton Rd – Anticipated start date Sept 16th
- School House – Drainage complete, mill and overlay to follow
- Matts Landing Rd – Drainage complete, mill and overlay to follow
NJDOT Funded Bridge Program – $ 632,000
- Causeway Bridge over Stow Creek – Pre Con scheduled for Sept 5th
August 14, 2011 Storm – 75% FEMA reimbursement - $ 907,000
- Harmony Road - Project schedule to begin October 1st
August 14, 2011 Storm – 80% Federal Highway reimbursement
- West Park Drive Embankment Stabilization – Anticipate awarding bid at the September 24th Freeholder meeting
NJDOT Funded Guiderail Program - $ 342,000
- Various locations throughout the County – Fall 2013 anticipated start date
NJDOT Funded Striping Program - $ 306,000
- Various locations throughout the County – Fall 2013 anticipated start date
![](/images/News%20&%20Events/road%20PR.jpg)
Freeholder Tony Surace (right), Liaison to the county Public Works Department, updates Freeholder Carlos Mercado (left) on the finishing steps of the Brewster Road (Vineland) improvement project.